Last week, the U.S. Senate voted 62-33 to pass the Bipartisan American Affordability and Jobs Act of 2026 (“BAAJA”), setting the stage for a consequential vote in the U.S. House of Representatives after the Thanksgiving recess. Heralded as “the most comprehensive permitting bill to date,”[1] BAAJA would reform key provisions of several federal laws that are critical for infrastructure development, namely, the National Environmental Policy Act (“NEPA”), Clean Water Act (“CWA”), Endangered Species Act (“ESA”), Federal Power Act (“FPA”) and National Historic Preservation Act (“NHPA”). BAAJA is poised to make meaningful changes to the legislative framework related to project development and, in so doing, reshape how federal agencies evaluate and approve projects.
Introduced by a bipartisan coalition of four senators on September 30, 2026, BAAJA marks the culmination of a decades-long effort to reform the federal environmental review and permitting processes. According to the bill’s sponsors, BAAJA will deliver cheaper energy, more jobs, and responsible growth across the United States.[2] On the environmental review and permitting front, the bill’s NEPA amendments would set one- or two-year deadlines for environmental reviews and deadlines for the permitting decisions that follow. The amendments would also limit the alternatives agencies must consider to those that meet both the project’s purpose and need and the non-Federal sponsor’s goals, while retaining the option of taking no action. The bill would also extend maximum CWA permit terms from five to 10 years, shorten the ordinary ESA consultation period from 90 to 60 days, and narrow the activities and effects subject to historic-preservation review. These changes are expected to make development schedules far more predictable.
How BAAJA Could Accelerate Energy Infrastructure Development
For energy infrastructure, BAAJA would facilitate grid expansion and modernization. The bill would expand the permitting authority of the Federal Energy Regulatory Commission (“FERC”) over qualifying interstate transmission facilities and strengthen coordinated transmission and generation-interconnection planning. Additionally, certain grid upgrades and natural gas pipeline improvements within existing corridors would be exempt from NEPA and NHPA review.
Data Centers: New Rules for Power Costs, Grid Interconnection and Financial Assurance
For data centers, BAAJA would place greater emphasis on infrastructure-cost responsibility. The bill would direct FERC to revise transmission-pricing policies to reflect embedded costs and a reasonable assessment of incremental costs, while prohibiting utilities from shifting retail incremental costs to other customers. For newly interconnecting data centers, utilities would require financial assurances or contributions before building necessary infrastructure, and service arrangements would provide for continued cost recovery even if the customer exits. The bill also recognizes the authority of states to condition service on procuring new generation or accepting limits on grid withdrawals, while generally preserving previously approved arrangements. For developers and investors, these provisions would make power procurement, financial security, and infrastructure-cost allocation central diligence considerations.
Permitting Litigation: Shorter Deadlines and New Limits on Project Challenges
To bring more certainty as to whether an approval is final and non-appealable, which is critical to financing projects, BAAJA would also generally impose 150-day filing windows for specified challenges under NEPA, NHPA, CWA and ESA, with differing triggers and exceptions. This is a dramatic improvement from the existing six-year Administrative Procedure Act statute of limitations. For NEPA and NHPA violations, the ordinary remedy would be remand without vacating approvals or enjoining projects, while preserving preliminary relief for qualifying violations of other laws. Separately, the bill would give qualifying developers additional remedies for federal interference and intentional patterns of disparate treatment, alongside judicial enforcement of certain permitting deadlines. This would provide more stability for both renewable and non-renewable energy projects when administrations change.
What to Watch as BAAJA Moves to the House
Despite levels of bipartisan support, approval of BAAJA by the House is not guaranteed. While the future of BAAJA remains uncertain, the legislative efforts being undertaken show that Congress is taking active steps to improve the legal framework to allow for a more efficient delivery of much-needed infrastructure improvements.
Sheppard is closely monitoring BAAJA’s fate in the House. Stay tuned for updates examining the potential implications for renewable energy, fossil fuels, digital infrastructure and related industries if the bill passes.
FOOTNOTES
[1] Bipartisan American Affordability and Jobs Act (BAAJA): Resource Hub, Bipartisan Pol’y Ctr. (Oct. 30, 2026), https://bipartisanpolicy.org/explainer/bipartisan-american-affordability-and-jobs-act-baaja-resource-hub/.
[2] Press Release, Sen. Shelley Moore Capito, Capito, Lee, Whitehouse, and Heinrich Introduce Bipartisan American Affordability and Jobs Act of 2026 (Sept. 30, 2026), https://www.capito.senate.gov/news/press-releases/capito-lee-whitehouse-and-heinrich-introduce-bipartisan-american-affordability-and-jobs-act-of-2026.